Do you need approval to renovate in NSW? Exempt, complying or DA

Every building project in NSW goes down one of three planning pathways. Working out which one applies before you design anything saves months and, sometimes, the cost of pulling work down.

Footing & Frame editors · Published 24 Nov 2026 · Last reviewed 24 Nov 2026

Rolled building plans and a scale ruler on a desk beside a laptop

At a glance

  • Exempt development: minor, low-impact work that needs no planning or building approval, provided it meets every standard in the State Policy.
  • Complying development: a fast-track, combined planning and construction approval issued by a council or a registered certifier.
  • Development application (DA): a merit assessment by council for everything else.
  • Planning approval is not the only sign-off. Sydney Water, your strata scheme and licensing rules can all apply as well.

Exempt development

Some minor renovations and low-impact works do not require planning approval. NSW Planning calls this exempt development, and the standards are set out in the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008.

The catch is that a project must meet all of the relevant standards. If it misses one, for example a height, a setback or a heritage restriction, it is not exempt and needs approval through one of the other two pathways.

Exempt does not mean unregulated. NSW Planning states that all work must still be structurally sound, be installed to the manufacturer's instructions and comply with the National Construction Code. Other laws continue to apply.

Complying development

Complying development is a combined planning and construction approval for straightforward projects. It is assessed against fixed standards, so if the design ticks every box it can be determined quickly by council or by a registered certifier, and the result is a complying development certificate (CDC).

It generally covers larger works than exempt development: many alterations and additions, new one and two storey houses and similar projects. The department publishes a Guide to Complying Development for homeowners, linked from its complying development page.

Not every property can use this pathway. Heritage items, some environmentally sensitive land and lots that do not meet minimum sizes are common exclusions.

Development application

If a project is neither exempt nor complying, it needs a development application to council. A DA is assessed on its merits against the council's local environmental plan and development control plan, and neighbours are usually notified.

Consent comes with conditions. For work that involves excavation or demolition near a boundary, one common condition is a dilapidation report on neighbouring buildings. After consent you still need a construction certificate before work starts and an occupation certificate at the end.

The sign-offs people forget

  • Sydney Water. If you are building over or next to a Sydney Water pipe, the plans need Sydney Water's approval. This is done through its Tap in service.
  • Strata. In an apartment or townhouse, by-laws and owners corporation approval apply on top of planning rules.
  • Licensing and insurance. In NSW, residential building work worth more than $5,000 in labour and materials needs a licensed contractor, and jobs over $20,000 need home building compensation cover.

Our approvals page lays these out as a checklist.

Questions people ask

Who decides which pathway my project is on?

The standards in the State Policy and your council's planning controls decide it. A registered certifier, a town planner or your council's duty planner can confirm it for a specific property.

Can exempt work still need an engineer?

Yes. Exempt development must still be structurally sound and comply with the National Construction Code, so structural elements still need to be designed properly.

Where do I lodge an application?

Complying development and development applications are lodged online through the NSW Planning Portal.

References

  1. NSW Planning: Planning approval pathways
  2. NSW Planning: Exempt development
  3. NSW Planning: Complying development
  4. NSW Planning Portal
  5. Sydney Water: Tap in (building plan approvals and diagrams)
  6. NSW Government: Contracts for residential building work

This article is general information for New South Wales. It is not engineering, legal or building advice for your property. Rules change: check the linked official sources and use qualified, licensed people.