Dilapidation reports: what they are and when Sydney projects need one
A dilapidation report is a dated record of the condition of the buildings and public land around a site, made before work begins. It exists for one reason: so that later arguments about damage can be settled with evidence.
Footing & Frame editors · Published 24 Nov 2026 · Last reviewed 24 Nov 2026

At a glance
- It records the existing condition of adjoining buildings, structures and public land before site work starts.
- It is commonly a condition of development consent, especially where there is excavation or demolition near a boundary.
- NSW's standard residential conditions call for it to be prepared by a suitably qualified engineer, with copies to the neighbours.
- A second report after construction shows whether anything changed.
What a dilapidation report is
The report is a survey, in photographs and written notes, of what is already there: cracks in walls and ceilings, the state of brickwork and render, paving, fences, retaining walls and, on the public side, the footpath, kerb and road.
It does not judge who caused existing defects and it is not a building inspection for a buyer. Its value is as a baseline. If a neighbour later says excavation next door cracked their wall, the before-and-after comparison shows whether the crack was already there.
When one is required
NSW Planning publishes standard conditions of consent for residential development. One of them, under "before building work commences", requires a dilapidation report prepared by a suitably qualified engineer detailing the structural condition of adjoining buildings, structures or works and public land.
The same document includes a post-construction dilapidation report, before the occupation certificate, to identify whether there has been structural damage to adjoining buildings and whether it resulted from the approved work.
Councils decide which conditions to apply to a particular consent. Excavation for basements, demolition and work close to a boundary are the usual triggers. Read the conditions on your own consent: they state what is required, by when and who must receive copies.
Access to the neighbour's property
A proper survey needs access inside and outside the adjoining property, which means asking the neighbours. Most agree, because the report protects them as much as the builder.
If access is refused, the standard condition allows the report to be based on what can be observed externally, with written evidence that all reasonable steps were taken to obtain access. The standard condition also requires adjoining owners to be given a copy of the report for their property before site work starts.
If you are the neighbour
- Say yes to the inspection and walk through with the engineer. Point out anything you want recorded.
- Take your own dated photographs of walls, ceilings, tiles and paving.
- Keep the copy you are given. If you notice new damage during the work, tell the builder and the principal certifier in writing, with photographs, straight away.
Questions people ask
Who pays for a dilapidation report?
The person carrying out the development, because the requirement sits on their consent.
Is a dilapidation report needed for a small renovation?
Only if it is a condition of your approval. Even when it is not, a simple photographic record of the neighbouring wall before excavation or demolition is cheap insurance.
Does the report cover council property?
The standard condition refers to public land as well as adjoining buildings, so footpaths, kerbs and road surfaces are normally included.
References
This article is general information for New South Wales. It is not engineering, legal or building advice for your property. Rules change: check the linked official sources and use qualified, licensed people.